FACTUAL PUBLIC INFORMATION

Bartlett ISD 2026 Election Information

Election Day – November 3, 2026

Voter-Approval Tax Rate Election and Two Proposed Refunding Bond Propositions

What is on the ballot in November?

Three separate decisions

The ballot contains one VATRE proposition and two refunding bond propositions. Voters may vote FOR or AGAINST each proposition independently.

 

 

Ballot item

What voters decide

Proposition A

VATRE - Whether to ratify a $0.7804 M&O rate and a $1.2804 total tax rate.

Proposition B

Whether to authorize up to $3.3 million in refunding bonds for eligible 2024 Maintenance Tax Notes.

Proposition C

Whether to authorize up to $1.0 million in refunding bonds for eligible 2024 Time Warrants.

Neutral-information notice

This publication provides factual information about proposed ballot measures. It does not advocate passage or defeat of any measure. Official election orders and ballot language control if any summary differs.

 

 

Why are these items on the November ballot?

Bartlett ISD is considering these measures because the district has approximately $3.3 million in outstanding liabilities, no available fund balance, and significant MTN and TWN payments currently being paid from the M&O budget. The VATRE would provide additional recurring operating revenue, while the bond propositions would move eligible note payments from M&O to I&S, creating greater financial stability without funding additional construction.

 
Election Overview

Bartlett ISD voters will consider three separate propositions on November 3, 2026. The measures address two different parts of the district's financial plan:

  1. The VATRE concerns recurring Maintenance and Operations (M&O) revenue.
  2. The two bond propositions concern whether eligible existing 2024 note obligations may be refunded and repaid through the Interest and Sinking (I&S) fund.
  3. Approval of one proposition does not automatically approve either of the others.
 
Why the district is considering the measures
District planning materials identify approximately $3.3 million in current liabilities: an approximately $1.8 million final construction-related balance and a $1.5 million February 2026 payroll loan. The construction figure is a planning amount that will decline or otherwise change as payments are made or settlement terms are finalized. Bartlett ISD reports that no fund balance is available to apply to these liabilities. The district must therefore use current and future revenue, spending reductions, negotiated repayment terms, other lawful financing, or a combination of those tools.
 
Existing M&O Pressure
The 2024 Maintenance Tax Notes and Time Warrants are currently paid from M&O, the same fund used for instruction, staffing, utilities, transportation, supplies, and other operations.
 

2026-2027 obligation

Scheduled M&O payment

Maintenance Tax Notes

$303,193.90

Time Warrants

$98,823.90

Combined

$402,017.80

These amounts are from the amended final debt-service schedules for the fiscal year ending June 30, 2027.
 
What M&O and I&S Mean

Fund

Primary purpose

How it relates to the ballot

M&O

Day-to-day school operations.

  • The VATRE would add recurring M&O revenue.
  • The existing MTN/TWN payments currently reduce M&O capacity.

I&S

Debt service on voter-authorized bonds.

  • The refunding propositions would authorize eligible MTN/TWN debt to be repaid through I&S after bonds are issued and closed.
 
VATRE: Rates, Revenue and Ballot Language
A voter-approval tax rate election (VATRE) asks voters whether the district may use the M&O rate adopted by the Board when that rate requires voter approval. If the proposition is not ratified, the district's M&O rate is limited to the applicable voter-approval rate.
 

Tax-rate component

Current / no VATRE

If VATRE is ratified

Change

M&O

$0.6604

$0.7804

+$0.1200

I&S

$0.5000

$0.5000

$0.0000

Total

$1.1604

$1.2804

+$0.1200

Rates are stated per $100 of taxable value.
 
Estimated Recurring Revenue
Under the district's current estimate, the additional twelve M&O pennies would generate approximately $600,000 each year:
  1. Approximately $220,000 in additional local M&O revenue.
  2. Approximately $380,000 in additional state aid from TEA.
The estimate is not guaranteed. Actual revenue will vary with taxable property values, collections, student attendance, and state school-finance formulas.
 
Proposition A - Official VATRE Ballot Language
Ratifying the ad valorem tax rate of $1.2804 in Bartlett ISD for the current year, a rate that will result in an increase of 18.174 percent in maintenance and operations tax revenue for the district for the current year as compared to the preceding year, which is an additional $0.12.
The ballot's 18.174 percent figure compares M&O tax revenue for the current year with the preceding year under the required ballot calculation. It is not a statement that every individual property-tax bill will increase by 18.174 percent.
 
VATRE Property-Tax Illustration
The following examples apply only the $0.12 VATRE difference and assume the residence receives the $140,000 state school-district homestead exemption. They do not include any other exemption or a change in appraised value.

Residence value

Assumed exemption

Taxable value

Estimated annual VATRE difference

Monthly equivalent

$140,000

$140,000

$0

$0

$0

$215,000

$140,000

$75,000

$90

$7.50

$300,000

$140,000

$160,000

$192

$16.00

Formula: taxable value / 100 x $0.12 = estimated annual VATRE difference.
 
Important Property-Specific Qualifications
  1. Actual tax bills depend on the taxable value certified by the appropriate appraisal district and all exemptions that apply to the property.
  2. The state school-district residence-homestead exemption is $140,000. A taxpayer may qualify for other exemptions.
  3. A school-district tax ceiling generally limits school taxes on a qualifying age-65 or disabled residence homestead. New improvements, changes in ownership or eligibility, and individual circumstances can affect the result.
  4. Businesses and non-homestead property do not receive the residence-homestead exemption.
  5. Qualified agricultural or open-space land is generally appraised using productivity value rather than market value; the property-specific effect depends on the appraisal record.
Historical Rate Comparison

School year

M&O

I&S

Combined

2022-23

$0.8546

$0.5000

$1.3546

2025-26

$0.6604

$0.5000

$1.1604

2026-27 if VATRE passes

$0.7804

$0.5000

$1.2804

The proposed $1.2804 total rate is $0.0742 per $100 lower than the district's $1.3546 combined rate in 2022-23.
 
Refunding Bond Propositions
The two bond propositions concern existing 2024 obligations. They do not authorize new construction projects. Each proposition is separate, so approval of one would not approve the other.
How to read the required tax statement
 
Each official bond proposition begins with 'THIS IS A PROPERTY TAX INCREASE.' The district's current plan assumes the I&S rate remains $0.5000. Future I&S rates are adopted annually and must be sufficient for debt service; actual taxes can also change when taxable value changes.
 
Proposition B - Official English Ballot Language
THIS IS A PROPERTY TAX INCREASE. The issuance of not to exceed $3,300,000 of Bartlett Independent School District refunding bonds for the purpose of refunding all or a portion of the principal, interest, and redemption premium on previously issued maintenance tax obligations of the District styled “Bartlett Independent School District Maintenance Tax Notes, Series 2024, dated March 1, 2024” and the levying of a tax sufficient to pay the principal and interest on the bonds and the cost of any credit agreements executed in connection with the Bonds.
 
Proposition C - Official English Ballot Language
THIS IS A PROPERTY TAX INCREASE. The issuance of not to exceed $1,000,000 of Bartlett Independent School District refunding bonds for the purpose of refunding all or a portion of the principal, interest, and redemption premium on previously issued time warrants of the District styled “Bartlett Independent School District Time Warrants, Series 2024, dated March 1, 2024” and the levying of a tax sufficient to pay the principal and interest on the bonds and the cost of any credit agreements executed in connection with the Bonds.
 
Is this another tax increase?
No. The words “THIS IS A PROPERTY TAX INCREASE” appear because Texas law requires that exact statement on every school district bond proposition. It is required even when the bonds would refinance existing debt and the district does not currently plan to increase the I&S tax rate. For Bartlett ISD, the proposals would move eligible MTN and TWN debt payments from M&O to I&S, while the current plan keeps the I&S rate at $0.50. Therefore, the statement is a legally required ballot label, not a statement that approval would automatically increase the district’s current I&S rate. Texas Education Code §45.003(b)–(b-1).
 
 
What the Refunding Bonds Would and Would Not Do

If a Refunding Proposition is Approved:

  1. The district would be authorized to issue refunding bonds for all or a portion of the eligible obligation identified in that proposition.
  2. After issuance and closing, eligible debt service could be paid through I&S rather than M&O.
  3. The M&O capacity released by the completed refunding could be available for lawful operating needs and the district's liability-repayment plan.
  4. Final amount, term, interest rate, issuance costs, timing, and eligibility would be determined through the financing process and validated by the district's financial adviser and bond counsel.

If a Refunding Proposition is Not Approved:

  1. The district would not have voter authorization to issue the refunding bonds described in that proposition.
  2. The related scheduled note payments would continue to be paid from M&O under the current documents unless another lawful arrangement is made.
  3. For 2026-27, the scheduled payments are $303,193.90 for the Maintenance Tax Notes and $98,823.90 for the Time Warrants.

What the Propositions Do Not Do:

  1. They do not erase the underlying debt; taxpayers continue to fund debt service through the applicable fund.
  2. They do not directly pay the separate approximately $3.3 million construction-related and payroll-loan liabilities.
  3. They do not authorize new construction projects.

Bond Authorization Amounts and Current Scheduled Debt:

Proposition

Maximum authorization

Existing obligation identified

2026-27 M&O payment

B

$3,300,000

Maintenance Tax Notes, Series 2024

$303,193.90

C

$1,000,000

Time Warrants, Series 2024

$98,823.90

 

How the Three Propositions Interact:

The table below describes planning consequences, not guaranteed outcomes. Bond-related M&O relief begins only after eligible bonds are issued and close. VATRE revenue and bond economics remain subject to the assumptions described elsewhere in this document.

Voter Result

VATRE Effect

Bond Effect

Planning Implication

VATRE and both bonds approved

Approximately $600,000 in estimated recurring annual M&O revenue.

Up to approximately $400,010 of 2026-27 scheduled M&O note payments could shift after closing.

Illustrative gross M&O capacity is about $1.0 million annually after closing, before timing, interest, issuance costs, and changes in estimates.

VATRE approved; bonds not approved

Estimated recurring VATRE revenue becomes available.

MTN and TWN payments remain in M&O.

The district gains the VATRE revenue but continues the scheduled M&O note payments.

VATRE not approved; one or both bonds approved

No additional $0.12 or estimated $600,000 annual VATRE revenue.

Only the eligible obligation approved by voters may move to I&S after closing.

The district may gain partial or full note-payment relief, but no VATRE revenue.

No propositions approved

Current/no-VATRE M&O rate remains the planning basis.

Both note categories remain in M&O.

The district must address liabilities and operating pressure through existing revenue, spending reductions, repayment agreements, other financing, or a combination.

If only one bond proposition is approved, only that proposition's eligible obligation may be refunded.

Illustrative Repayment Context

At $600,000 per year, applying every incremental VATRE dollar to a $3.3 million starting liability would be a mathematical paydown of approximately 5.5 years before interest or changes in the balance. If both bonds close and release roughly $400,000 of annual M&O capacity, the combined gross planning capacity would be about $1.0 million per year and the mathematical period would be about 3.3 years.

 

Illustration only
These are not promised payoff dates. Actual results depend on repayment agreements, interest, bond timing and costs, lawful uses of funds, revenue performance, and the district’s operating needs.
 

Frequently asked questions

1.  Why are there three propositions?

Bartlett ISD has outstanding liabilities that cannot be paid with the current M&O revenue. These propositions would generate additional M&O revenue the district would use to pay down the 3.3 million in liabilities. The VATRE addresses recurring M&O revenue. Proposition A addresses the 2024 Maintenance Tax Notes. Proposition B addresses the 2024 Time Warrants. Voters decide each separately.

2. Does the VATRE change the I&S rate?

No. The VATRE proposition changes the M&O rate by $0.12. The district's current plan keeps I&S at $0.5000.

3. What does the 18.174 percent language mean?

It is the required comparison of M&O tax revenue for the current year with the preceding year under the ballot calculation. An individual's bill depends on taxable value and exemptions, so the percentage is not a uniform household tax-bill increase.

4. Why can $0.12 generate about $600,000 when local taxes add about $220,000?

Texas school funding formulas can provide additional state aid for eligible Tier II tax effort. The district estimate includes about $220,000 local revenue and $380,000 state aid. The final amount can vary.

5. Is the proposed total rate higher than the district's 2022-23 rate?

No. The proposed $1.2804 combined rate is $0.0742 lower than the $1.3546 combined rate adopted for 2022-23.

6. Does a $140,000 home automatically pay no school tax?

The example assumes a $140,000 residence homestead that qualifies for the $140,000 state school-district exemption and has no remaining taxable value. Property-specific records and other taxing units may produce a different overall tax bill.

7. Will a qualifying age-65 or disabled homeowner pay more?

A school-district tax ceiling generally limits school taxes on a qualifying residence homestead. Improvements, ownership or eligibility changes, and individual circumstances can affect the result. The appraisal district or tax assessor should provide a property-specific answer.

8. Why does each bond proposition say 'THIS IS A PROPERTY TAX INCREASE' if the I&S rate is planned to stay at $0.50?

That sentence appears in the official ballot language. The district's current financing assumption is no increase above the existing $0.5000 I&S rate. The words “THIS IS A PROPERTY TAX INCREASE” appear because Texas law requires that exact statement on every school district bond proposition. It is required even when the bonds would refinance existing debt and the district does not currently plan to increase the I&S tax rate. Future rates are adopted annually, taxable values can change, and the levy must be sufficient for bond debt service.

9. Do the bond propositions eliminate debt?

No. They would change the authorized repayment source for eligible existing obligations after refunding bonds close. The debt service payment would move from the M&O budget and would continue through I&S.  It does not decrease or increase the debt.

10. Do the bonds pay the approximately $3.3 million liabilities?

No. Bond proceeds would refund eligible Maintenance Tax Notes or Time Warrants, depending on the proposition approved. They would not directly pay the separate construction-related balance or payroll loan.

11. Do the November bond propositions include new construction?

No. The official propositions are limited to refunding the identified 2024 obligations and related authorized costs.

12. What happens if only one bond proposition passes?

Only the eligible obligation named in that proposition could be refunded. The other note category would remain scheduled in M&O.

13. Is the approximately $600,000 VATRE estimate guaranteed?

No. It is a planning estimate based on current local values, collection assumptions, state funding formulas, attendance, and other inputs.

14. What controls are expected regardless of the vote?

District planning materials identify a board-approved repayment plan, monthly public financial reporting, staffing and purchasing controls, cash-flow monitoring, and publication of material changes in assumptions.

Voting information

Milestone

Date / time

Voter registration deadline

October 5, 2026

Early voting in person

October 19-30, 2026

Election Day

November 3, 2026 | 7:00 a.m.-7:00 p.m.

County-specific voting locations, weekend hours, and other election details will be listed in the official election notice and posted at bartlett.txed.net.

Sources and document notes

Official public sources

Accuracy and legal-review note

Financial amounts described as estimates or planning figures may change as payments are made, agreements are finalized, taxable values or state formulas change, or bonds are priced. Official election orders, notices, and ballot language control. Before district-funded publication or mailing, district counsel and bond counsel should confirm the final text, current liability balance, financing assumptions, official Spanish translations, and election locations and hours.

 

Public-purpose statement

This information is intended to enable informed voter decisions through factual information. It does not advocate passage or defeat of a ballot measure.



The information below contains information for previous general elections.